Project Timeline

A chronological record of property, infrastructure, government, and records-request activity.

Representative image. Not an official rendering or photograph of Project Mustang.

Timeline entries are added when supported by documentary evidence or clearly labeled attributable public statements.

April 2021

Property acquisition

NMCV Taylor Property Investors LLC acquired the 486.392-acre tract through recorded instrument 2021055203.

January 2023

Matterhorn litigation / easement activity

A lis pendens was filed concerning the Matterhorn Express pipeline corridor.

December 2023 – April 2024

Pipeline easement resolved

Final easement-related instruments were executed and the lis pendens was later released.

2025

Loan renewal

Recorded loan-renewal documents continued the property financing.

June 2026

Loan extension

Recorded instrument 2026047350 extended the existing loan and documented the outstanding balance.

July 23, 2026

City executive-session discussion

Approved meeting minutes record a closed executive-session discussion of Project Mustang and Project Meridian. Council reconvened afterward with no Mustang-specific action documented.

August 7, 2026

Employment Center zoning request submitted

PZ 2026-2715 seeks Employment Center zoning for approximately 664.572 acres with concurrent voluntary-annexation review.

August 13, 2026

Big Watt Digital and PH Digital named in City agenda

The City Council agenda identifies Big Watt Digital LLC and PH DIGITAL DATA CENTER DEVELOPMENT LLC in a closed-session item described as “formerly Project Mustang.” The agenda confirms scheduled deliberation, not a final approval or incentive agreement.

August 18, 2026

Planning & Zoning hearing scheduled

The documented review path schedules the P&Z hearing for PZ 2026-2715 on August 18, 2026.

September 10, 2026

City Council hearing scheduled

The documented review path schedules City Council consideration/hearing for the Employment Center plan on September 10, 2026.