The October development agreement now provides the most current negotiated water and wastewater framework for Taylor Technology Campus, replacing several August planning-stage estimates for purposes of describing the current agreement terms.
Last verified October 9, 2026
What the Current Project Records Show
October 2026 development agreement
Closed-loop HVAC / 1.575 million-gallon collective initial fill
All building HVAC systems are to use closed-loop cooling for industrial use. The agreement caps the combined closed-loop HVAC system volume / one-time initial fill at 1,575,000 gallons collectively for all buildings on the Property.
Current agreement
October 2026 development agreement
Up to 150,000 GPD reclaimed-water service
The agreement requires City service capacity of up to 0.15 MGD (150,000 gallons per day) average daily demand of reclaimed water, subject to agreement conditions.
Current agreement
October 2026 development agreement
22,500 GPD potable-water capacity
The agreement provides for up to 0.0225 MGD (22,500 gallons per day) average daily potable-water demand, principally for permitted domestic/non-industrial uses.
Current agreement
October 2026 development agreement
69,000 GPD wastewater capacity
The agreement provides for City acceptance, conveyance and treatment of domestic wastewater up to 0.069 MGD (69,000 gallons per day) average daily flow.
Current agreement
October 2026 development agreement
Developer contribution for at least 1.0 MGD reclaimed-water improvements
The agreement defines the Developer’s contribution around Mustang Creek reclaimed-water improvements sized to produce not less than 1.0 MGD. City materials state the City may retain capacity beyond the campus demand for other users.
Current agreementOctober 2026 City packet / agreement
Pending TCEQ wastewater-discharge application referenced
City materials state the property has a pending TCEQ wastewater-discharge permit application and require its withdrawal within five business days after issuance of the first site-development permit, unless an agreement termination event has occurred. The permit number and filing entity remain to be obtained.
New records lead
Important Qualification
The August Employment Center Plan used different planning-stage figures, including approximately 125,000 GPD reuse water, 13,450 GPD domestic water and up to 5 million gallons of initial HVAC fill per building. Those figures remain part of the historical record, but the October agreement provides the newer negotiated service/initial-fill terms above. A fully executed signature copy has not yet been archived here.
What Is Still Unknown
- Actual water and reclaimed-water consumption at each phase and full buildout.
- Whether later engineering changes requested service capacities within the agreement’s amendment/termination framework.
- Final routing, schedule and cost of off-site water, reclaimed-water and wastewater improvements.
- The TCEQ wastewater-discharge application number, applicant/entity, proposed outfall and technical contents.
- Whether/when the required wastewater-discharge application withdrawal occurs after the triggering permit milestone.
Official recordFinal figures unresolved
Primary sources: October 2026 Taylor Technology Campus development agreement / City Council packet and City project page; August 2026 Employment Center materials retained as historical comparison. Documents & sources →