NMCV Taylor Property Investors LLC
Confirmed owner of the 486.392-acre tract through recorded property instruments.
ConfirmedThe site, property, entities, and currently documented project facts.
Representative image. Not an official rendering or photograph of Project Mustang.
Project Mustang is a proposed large-scale data-center development east of Taylor, Texas.
This site tracks the project through property records, government records, regulatory filings, technical analysis, and public-information requests. Facts are separated from public claims, reasonable inferences, and unresolved questions.
| Parcel | Area | Owner | Location / Notes |
|---|---|---|---|
| R006648 | 486.392 acres | NMCV Taylor Property Investors LLC | 3301 FM 112; Hardy Pace Survey A-493 |
| R006650 | 178.18 acres | Morris & Barbara Zieschang | FM 112; contiguous with R006648 |
Combined identified site area: 664.572 acres.
Confirmed landowners and parties identified in official City records are tracked separately. The exact contractual relationships among the property owners, Big Watt Digital LLC, PH DIGITAL DATA CENTER DEVELOPMENT LLC, and any other developer or end user remain under investigation.
Confirmed owner of the 486.392-acre tract through recorded property instruments.
ConfirmedNamed in the City of Taylor August 13, 2026 agenda in connection with “formerly Project Mustang.” The agenda confirms scheduled economic-development/legal deliberation, not a final agreement or approval.
Officially IdentifiedNamed in the City of Taylor August 13, 2026 agenda in connection with “formerly Project Mustang.” Its exact project role and contractual relationship remain under investigation.
Officially IdentifiedLast verified September 5, 2026
The City says annexation remains under discussion as a potential mechanism for imposing negotiated regulations on matters such as noise, water use, setbacks and community benefits. The City’s current Project Mustang page describes proposed annexation-related standards including a 1,100+ foot buffer between data-center/cooling/power-generation equipment and the nearest residence and an “EPA Tier 4” air-quality standard. Those are City-described proposed terms, not current enforceable Project Mustang requirements.
Last verified September 5, 2026
Planning materials and the August 18 Planning & Zoning hearing now provide a much clearer picture of the proposed campus. These figures describe the current concept; they are not final permits, equipment selections, or operating conditions.
Project representatives described roughly 1,040 MW of on-site natural-gas generation supporting approximately 700 MW of data-center load, with initial operation potentially isolated from the electric grid.
Publicly stated at hearingThe submitted equipment schedule lists 84 to 112 gas-fired units at 12.5 MW each. If every listed unit were installed, that schedule implies approximately 1.05–1.40 GW of aggregate nameplate capacity, which is broader than the approximately 1,040-MW hearing figure.
Proposal + calculationThe concept includes gas-generation yards, stacks up to approximately 125 feet, diesel backup and black-start generation, BESS, substations, gas infrastructure, urea/fuel-related storage, and cooling/radiator systems.
Proposed / documentedWilliamson County’s August 18 public-records production confirms that Kimley-Horn was coordinating with County infrastructure staff over a future arterial alignment by May 2026. The records document a June 22 meeting, a July 8 County engineering request for a detailed 136-foot ROW resubmittal, and a July 22 revised exhibit showing two potential future County road paths.

Read the Transportation Findings → View the County Production →