The August 7 Project Mustang Employment Center Plan now provides project-specific information about the proposed electrical system, substations and utility coordination.
Last verified September 5, 2026
What the Current Project Records Show
Official submittal
Oncor identified as electric provider
Kimley-Horn states that Oncor Electric Delivery is the electric provider for the site and that the development has been in frequent contact with Oncor. Additional service information remains to be clarified.
Proposed / documented
Official submittal
Substations may be located throughout the campus
The EC Plan allows electrical substations, switchyards, transformers and associated electrical infrastructure throughout the property as needed to support the closed-campus employment center.
Proposed / documented
Derived from submitted equipment schedule
Potential generation scale is very large
The plan lists 84–112 gas-fired units at 12.5 MW each. Simple arithmetic implies approximately 1.05–1.40 GW of aggregate gas-generator nameplate capacity if all listed units are installed. This is not a statement of continuous output or final installed capacity.
Calculated from proposal
Hearing disclosure
Approximately 700 MW data-center load / 1,040 MW on-site generation
At the August 18 hearing, project representatives described approximately 700 MW of data-center load and roughly 1,040 MW of on-site generation. They also described initial operation as potentially isolated from the electric grid and said the generation is not intended for exporting or selling power.
Hearing disclosure
What Is Still Unknown
- Final Project Mustang electric load and peak demand.
- Final Oncor interconnection configuration, transmission upgrades and substation design.
- Any final ERCOT interconnection arrangement attributable to this project.
- Who will fund project-driven off-site electrical infrastructure.
- Final relationship between grid service and the proposed on-site generation system.
Official recordCalculated / statedStill unresolved
Primary sources: Project Mustang Employment Center Plan Submittal, Kimley-Horn, August 7, 2026, City of Taylor case PZ-2026-2715; and August 18, 2026 Taylor Planning & Zoning hearing disclosures. Proposed figures remain subject to later engineering, permitting and site-plan review. Documents & sources →