84–112 gas engines / stacks
The submitted plan lists 84 to 112 gas-unit engines/stacks, with a stated per-unit capacity of 12.5 MW.
Proposed / documentedNatural-gas generation, backup systems, emissions, and air quality.
Representative photograph of backup generators and electrical infrastructure at a data center in Mesa, Arizona. Not Project Mustang. Photo: Rsparks3 / Wikimedia Commons (CC0 1.0).
The Project Mustang submittal now describes a substantial proposed on-site generation system rather than merely identifying generation as a possible project feature.
Last verified September 5, 2026
The submitted plan lists 84 to 112 gas-unit engines/stacks, with a stated per-unit capacity of 12.5 MW.
Proposed / documentedMultiplying the stated unit count by 12.5 MW yields approximately 1,050 to 1,400 MW of aggregate gas-generator nameplate capacity if all listed units are installed. This is a calculated range, not a confirmed operating output.
CalculatedThe plan lists 3-MW diesel-fired backup generators and two life-safety backup generators per data-center building. Planning materials also depict emergency/life-safety backup generation.
Proposed / documentedProject representatives described roughly 1,040 MW of on-site generation at the August 18 hearing. The separate Employment Center equipment schedule lists 84–112 units at 12.5 MW each, which implies a broader 1.05–1.40 GW theoretical nameplate range if every listed unit were installed. The discrepancy remains an important item to reconcile as engineering advances.
Hearing + submitted schedulePlanning disclosures allow gas-generation stacks up to approximately 125 feet. Exact stack coordinates, diameters, exhaust temperatures and final source locations have not been published.
Proposed / documentedThe current concept includes diesel backup generation for data-center buildings and separate black-start diesel generation in addition to the natural-gas generation system.
Proposed / documentedThe EC Plan states that gas infrastructure must comply with applicable federal, state and local requirements, including applicable air-quality permitting. It also contains an emissions provision for generators and other non-road equipment. These provisions establish proposed compliance requirements; they do not establish that final equipment selections or Project Mustang-specific air permits have been approved.
Primary sources: Project Mustang Employment Center Plan Submittal, Kimley-Horn, August 7, 2026, City of Taylor case PZ-2026-2715; and August 18, 2026 Taylor Planning & Zoning hearing disclosures. Proposed figures remain subject to later engineering, permitting and site-plan review. Documents & sources →